JASA
No. URAIAN KODE SATUAN HARGA SATUAN (Rp)
1. Pekerja (L01) Jam 11,000.00
2. Tukang (L02) Jam 12,000.00
3. M a n d o r (L03) Jam 15,000.00
4. Operator (L04) Jam 13,500.00
5. Pembantu Operator (L05) Jam 11,000.00
6. Sopir / Driver (L06) Jam 12,500.00
7. Pembantu Sopir / Driver (L07) Jam 11,000.00
8. Mekanik (L08) Jam 13,500.00
9. Pembantu Mekanik (L09) Jam 11,000.00
10. Kepala Tukang (L10) Jam 13,000.00

BAHAN
No. URAIAN KODE SATUAN HARGA SATUAN (Rp)
1 Pasir Pasang (Sedang) M01b M3 232,500.00
2 Pasir Beton (Kasar) M01a M3 250,000.00
3 Pasir Halus (untuk HRS) M01c M3 270,000.00
4 Pasir Urug (ada unsur lempung) M01d M3 155,000.00
5 Batu Kali / Batu Mangga M02 M3 195,500.00
6 Agregat Pecah Kasar M3 210,000.00
7 Agg. Halus LP A M3 262,000.00
8 Agregat Lolos # 1 " M3 231,500.00
6 Lolos screen1 ukuran ( 0 - 5) M3 226,500.00
7 Lolos screen2 ukuran ( 0 - 5) M3 226,500.00
7 Lolos screen2 ukuran ( 5 - 10) M3 231,500.00
8 Lolos screen2 ukuran ( 10 - 20) M3 206,650.00
9 F i l l e r M05 Kg 1,440.00
10 Kerikil M06 M3 264,500.00
11 G r a v e l M07 M3 315,000.00
10 Bahan Tanah Timbunan M08 M3 74,000.00
11 Bahan Pilihan M09 M3 150,000.00
12 Aspal M10 KG 12,000.00
13 Kerosen / Minyak Tanah M11 LITER 10,185.00
14 Semen / PC  (50kg) M12 Zak 72,000.00
21 Semen / PC  (kg) M12 Kg 1,440.00
15 Besi Beton M13 Kg 12,000.00
22 Kawat Beton M14 Kg 18,000.00
16 Kawat Bronjong M15 Kg 26,000.00
23 S i r t u M16 M3 156,300.00
24 Cat Marka (Non Thermoplas) M17a Kg 59,200.00
25 Cat Marka (Thermoplastic) M17b Kg 64,200.00
26 P a k u M18 Kg 17,000.00
27 Kayu Perancah M19 M3 1,700,000.00
28 B e n s i n M20 LITER 8,000.00
29 S o l a r M21 LITER 10,000.00
30 Minyak Pelumas / Olie M22 LITER 30,000.00
30 Plastik Filter M23 M2 15,000.00
31 Pipa Galvanis Dia. 1.6" M24 Batang 154,000.00
31 Pipa Porus M25 M' 40,000.00
31 Agr. Base Kelas A M26 M3 277,332.73
32 Agr. Base Kelas B M27 M3 239,710.24
33 Agr. Base Kelas S M28 M3 295,350.88
34 Geotextile M30 M2 35,000.00
35 Aspal Emulsi M31 Kg 5,000.00
36 Gebalan Rumput M32 M2 3,500.00
37 Thinner M33 LITER 12,000.00
38 Glass Bead M34 Kg 28,600.00
39 Pelat Rambu (Eng. Grade) M35a BH 176,000.00
40 Pelat Rambu (High I. Grade) M35b BH 216,500.00
41 Rel Pengaman M36 M' 412,500.00
34 Baja Tulangan (Polos) U24 M39a Kg 12,800.00
35 Baja Tulangan (Ulir) D32 M39b Kg 13,200.00
36 Kapur M40 M3 40,000.00
37 Plamir tembok M41 M3 25,000.00
37 Cat penutup  M41kg Kg 25,000.00
36 Cat M42 Kg 25,000.00
38 Pemantul Cahaya (Reflector) M43 Bh. 12,600.00
37 Pasir Urug M44 M3 151,800.00
39 Arbocell M45 Kg. 32,000.00
38 Baja Bergelombang M46 Kg 12,500.00
39 Baja Struktur M48 Kg 12,800.00
41 Tiang Pancang Baja M49 M' 25,247.37
40 Tiang Pancang Beton Pratekan M50 M3 423,957.93
42 Kawat Las M51 Dos 16,000.00
41 Pipa Baja M52 Kg 15,000.00
43 Minyak Fluks M53 Liter 6,237.00
42 Bunker Oil M54 Liter 3,000.00
44 Asbuton Halus M55 Ton 325,000.00
43 Baja Prategang M56 Kg 8,000.00
45 Baja Tulangan (Polos) U32 M57a Kg 12,800.00
44 Baja Tulangan (Ulir) D39 M39c Kg 13,200.00
46 Baja Tulangan (Ulir) D48 M39d Kg 9,000.00
45 PCI Girder L=17m M58a Buah 86,000,000
47 PCI Girder L=21m M58b Buah 97,000,000
46 PCI Girder L=26m M58c Buah 124,000,000
48 PCI Girder L=32m M58d Buah 157,000,000
47 PCI Girder L=36m M58e Buah 168,000,000
49 PCI Girder L=41m M58f Buah 192,000,000
48 Beton K-300 M59 M3 1,196,898.54
49 Cerucuk M61 M 27,000
51 Elastomer  M62 buah 300,000
50 Bahan pengawet: kreosot M63 liter 5,000
52 Mata Kucing M64 buah 75,000
51 Anchorage M65 buah 480,000
53 Anti strpping agent M66 Kg 24,000.00
52 Bahan Modifikasi M67 Kg 1,000.00
54 Beton K-500 M68 M3 2,331,461.48
53 Beton K-400 M69 M3 2,163,023.01
55 Ducting (Kabel prestress) M70 M' 150,000
54 Ducting (Strand prestress) M71 M' 50,000
55 Multipleks 12 mm M73 Lbr 181,500.00
57 Elastomer jenis 1 M74a buah 385,500.00
56 Elastomer jenis 2 M74b buah 650,000.00
58 Elastomer jenis 3 M74c buah 838,000.00
57 Expansion Tipe Joint Asphaltic Plug M75d M 1,000,000.00
59 Expansion Join Tipe Rubber M75e M 1,200,000.00
58 Expansion Join Baja Siku M75f M 275,000.00
60 Marmer M76 Buah 400,000.00
59 Kerb Type A M77 Buah 45,000.00
61 Paving Block M78 Buah 40,000.00
60 Mini Timber Pile M79 Buah 27,000.00
62 Expansion Joint Tipe Torma M80 M1 1,200,000.00
61 Strip Bearing M81 Buah 229,500.00
63 Joint Socket Pile 35x35 M82 Set 607,500.00
62 Joint Socket Pile 16x16x16 M83 Set 67,500.00
64 Mikro Pile 16x16x16 M84 M1 60,750.00
63 Matras Concrete M85 Buah 405,000.00
65 Assetilline M86 Botol 229,500.00
64 Oxygen M87 Botol 114,750.00
66 Batu Bara M88 Kg 700
37 Pipa Galvanis Dia 3" M24a M 100,000.00
38 Pipa Galvanis Dia 1,5" M24b M 67,000.00
38 Agregat Pecah Mesin 0-5 mm M91 M3 231,500.00
39 Agregat Pecah Mesin 5-10 & 10-20 mm M92 M3 231,500.00
39 Agregat Pecah Mesin 20-30 mm M93 M3 231,500.00
40 Joint Sealent M94 Kg 34,100.00
40 Cat Anti Karat M95 Kg 35,750.00
41 Expansion Cap M96 M2 6,050.00
41 Polytene 125 mikron M97 Kg 19,250.00
42 Curing Compound M98 Ltr 38,500.00
42 Kayu Acuan M99 M3 1,700,000.00
43 Additive M67a Ltr 38,500.00
43 Casing M100 M2 9,000.00
44 Pasir Tailing M3 259,000.00
44 Polimer 45,000.00
45 Batubara kg 500
45 Kerb jenis 1 Buah 45,000.00
46 Kerb jenis 2 Buah 50,000.00
46 Kerb jenis 3 Buah 55,000.00
47 Bahan Modifikasi Kg 75,000.00
47 Aditif anti pengelupasan Kg 30,000.00
48 Bahan Pengisi (Filler) Tambahan Kg 1,440.00
48 Asbuton yang diproses Kg 30,000.00
49 Elastomer Alam Kg 30,000.00
49 Elastomer Sintesis Kg 30,000.00
50 Anchorage
- hidup bh 750,000.00
- mati bh 400,000.00
51 Kabel Prategang
- Baja Prategang Kg 8,000.00
52 Epoxy Bahan Penutup (sealant) Kg 34,100.00


ALAT
URAIAN BIAYA
No. KODE HP KAP. SEWA
ALAT/JAM
(di luar PPN)
1 ASPHALT MIXING PLANT E01 294 60 T/Jam 6,657,147.66
2 ASPHALT FINISHER E02 72.4 10 Ton 787,635.47
3 ASPHALT SPRAYER E03 4 850 Liter 62,372.24
4 BULLDOZER 100-150 HP E04 155 -   -   659,500.98
5 COMPRESSOR 4000-6500 L\M E05 60 5,000.00 CPM/(L/m) 162,387.59
6 CONCRETE MIXER 0.3-0.6 M3 E06 20 500 Liter 120,369.52
7 CRANE 10-15 TON E07 138 15 Ton 505,957.21
8 DUMP TRUCK 3.5 TON E08 100 6 Ton 288,196.98
9 DUMP TRUCK 10 TON E09 190 10 Ton 479,014.55
10 EXCAVATOR 80-140 HP E10 133 0.9 M3 631,976.57
11 FLAT BED TRUCK 3-4 M3 E11 190 10 ton 479,884.86
12 GENERATOR SET E12 180 135 KVA 417,512.49
13 MOTOR GRADER >100 HP E13 135 10,800.00 - 588,299.27
14 TRACK LOADER 75-100 HP E14 70 0.8 M3 281,625.86
15 WHEEL LOADER 1.0-1.6 M3 E15 96 1.5 M3 469,313.66
16 THREE WHEEL ROLLER 6-8 T E16 55 8 Ton 352,230.16
17 TANDEM ROLLER 6-8 T. E17 82 8.1 Ton 404,880.16
18 TIRE ROLLER 8-10 T. E18 100.5 9 Ton 440,955.16
19 VIBRATORY ROLLER 5-8 T. E19 82 7.05 Ton 404,880.16
20 CONCRETE VIBRATOR E20 5.5 25 - 41,601.24
21 STONE CRUSHER E21 220 60 T/Jam 1,114,336.26
22 WATER PUMP 70-100 mm E22 6 -   -   38,630.51
23 WATER TANKER 3000-4500 L. E23 100 4,000.00 Liter 254,312.66
24 PEDESTRIAN ROLLER E24 8.8 835 Ton 75,539.81
25 TAMPER E25 4.7 121 Ton 40,200.44
26 JACK HAMMER E26 0 1,330.00 - 28,584.69
27 FULVI MIXER E27 345 2,005.00 - 920,280.09
28 CONCRETE PUMP E28 100 8 M3 313,635.16
29 TRAILER 20 TON E29 175 20 Ton 485,477.62
30 PILE DRIVER + HAMMER E30 25 2.5 Ton 276,323.83
31 CRANE ON TRACK 35 TON E31 125 35 Ton 593,302.36
32 WELDING SET E32 40 250 Amp 109,462.53
33 BORE PILE MACHINE E33 150 2,000.00 Meter 804,578.54
34 ASPHALT LIQUID MIXER E34 5 1,000.00 Liter 72,560.82
35 TRONTON E35 150 15 Ton 533,635.72
36 COLD MILLING E36 248 1,000.00 m 1,677,757.26
37 ROCK DRILL BREAKER E37 3 - - 307,971.45
38 COLD RECYCLER E38 900 2,200.00 M 6,327,145.40
39 HOT RECYCLER E39 400 3 M 7,614,968.10
40 AGGREGAT (CHIP) SPREADER E40 115 3.5 M 534,145.34
41 ASPHALT DISTRIBUTOR E41 115 4,000.00 Liter 345,017.00
42 SLIP FORM PAVER E42 105 2.5 M 541,010.96
43 CONCRETE PAN MIXER E43 134 600 Liter 650,623.83
44 CONCRETE BREAKER E44 290 20 m3/jam 820,875.94
45 ASPAHLT TANKER E45 190 4,000.00 liter 543,350.79
46 CEMENT TANKER E46 190 4,000.00 liter 503,350.79
47 CONDRETE MIXER (350) E47 20 350 liter 76,573.00
48 VIBRATING RAMMER E48 4.2 80 KG 45,296.22
49 TRUK MIXER (AGITATOR) E49 220 5 M3 627,563.28
50 BORE PILE MACHINE E50 125 60 CM 655,052.88
51 CRANE ON TRACK 75-100 TON E51 200 75 Ton 994,710.95
52 BLENDING EQUIPMENT E52 50 30 Ton 227,428.58
53 CONCRETE PAVER E65 105 2.5 M 541,010.96
54 BATCHING PLANT E66 134 60,000.00 Liter 797,041.22
55 CHAIN SAW 75,000.00